Construction loans are usually advanced in stages. Before each draw, the lender wants an independent account of how far the work has progressed. AREAS carries out progress inspections on residential construction across Southern Ontario and the Algoma District, reporting the work in place on site against the budget and draw schedule the lender is working from.
How lenders use a progress inspection
The lender sets the draw process. It decides how many draws there are, which stage of work each one covers and what the inspection report must show. The report gives the lender an account of the work completed at the date of the visit, set against the stages in the draw schedule and supported by photographs. The lender then decides what to advance. Everyone else on the project, from the owner to the builder, works to that process, so it helps to understand it before the first visit.
Start with the lender's instructions
Before the first visit, we need the lender's instructions and any form it requires. Lenders differ on the format, the level of detail and who must order the inspection. If the loan was arranged through a broker, the broker can usually point you to the lender's instructions. For the appraisal side of mortgage lending, see appraisals for financing and refinancing.
The budget and draw schedule
The budget and draw schedule are the measuring stick for each visit. The inspection compares what is on site with the stages already funded and the stage the next draw would cover. A clear cost breakdown, with line items that match how the house is actually being built, makes each report easier to prepare and easier for the lender to read. If the budget or schedule changes, send the revised version, agreed with the lender, before the next visit.
Site access and safety
Construction sites change between visits. Give us a site contact who can let us in, confirm the access hours and tell us about any safety requirements on site. The inspection needs to see the work the draw relates to, so make sure each floor and area is reachable. If some of the work cannot be seen, for example framing that has already been closed in, the report needs to say so, and that can affect what the lender is prepared to advance.
What a progress inspection does not cover
A progress inspection reports the stage of construction for a lending decision. It is not a municipal building inspection, an engineering review or a check of workmanship, and it does not confirm that the project meets the building code or the permit. Those roles belong to the building department and to the project's designers, engineers and builder.
Booking repeat visits
Most projects need an inspection before each draw. Tell us when you expect to request the next advance, and let us know early if the lender changes or the project stalls, so the next report starts from an accurate record.
What to have ready
- Lender's instructions and any inspection form it requires
- Construction budget or cost breakdown
- Draw schedule showing the stage of work tied to each advance
- Building permit and the plans the lender has on file
- Earlier progress inspection reports, if another inspector started the file
- Site contact, access hours and any site safety requirements
- A short note of the work completed since the last draw
Questions
Does a progress inspection mean the lender will release the draw?
No. The inspection reports what was observed on site at the date of the visit. The lender decides whether to advance funds, and how much.
Is a progress inspection the same as a building inspection?
No. Municipal building inspections deal with the building code and the permit. A progress inspection reports the stage of construction for the lender. It does not certify workmanship, code compliance or structural adequacy.
Can the owner or builder book the inspection directly?
Ask the lender first. Many lenders arrange progress inspections themselves or set out how they must be ordered. The lender's instructions decide who the client is and where the report goes.